Large-Load Grid Integrationv1.31
/
Download PDF DOI

Orientation

Upcoming Dates and Events: A 12–18 Month Watchlist#

Everything in this report eventually resolves into a calendar. This section is that calendar — the decisions, filings, and market events that will determine which of the eight problems get answered and which remain open a year and a half from now. It sits before Section 1 by design: a reader who takes nothing else from the report should still know what arrives and when.

Two cautions on reading it. First, the entries mix categories on purpose — compliance deadlines, market outcomes, rulemaking milestones, and the years NERC flags as the onset of elevated reliability risk — because developers and planners navigate that mixture as a single decision environment. Second, the confidence tag distinguishes a date someone must legally meet from a date someone currently intends to meet. Items tagged Emerging in particular signal direction of travel rather than schedule: rulemakings slip, standards get remanded, and a single court decision on the co-location or jurisdiction questions could reorder much of the 2027 column.

The next 90 days — July to September 2026#

The densest stretch on the calendar. Four filings inside a month will show, for the first time, whether the RTOs intend to defend their tariffs or replace them.

DateEventWhat it decidesTag
Jul 20, 2026RTO/ISO resource-adequacy informational reports due to FERC — deadline passedFirst formal statement from each RTO on whether it can actually serve its queue (§2)SETTLED
Jul 24, 2026ERCOT TSP/DSP submissions due — Batch Zero eligibilityFixes the Batch Zero population and the base-load MW allocation (§1, §5)SETTLED
Aug 3, 2026NERC Level 3 Essential Action Alert responses dueReveals the true extent of ride-through non-compliance across the fleet (§4)SETTLED
Aug 3, 2026§206 abeyance requests due (45 days)Whether the common August 17 deadline holds across all six regions (§7)LIKELY
**Aug 17, 2026****RTO/ISO §206 show-cause responses and briefs due (60 days)**One of the year's most consequential filings: defend the existing tariff or propose the replacement (§5, §6, §7)SETTLED
Sep 10 – Oct 9, 2026PJM reliability backstop procurement window (per the June 30 design paper)Whether backstop capacity can be procured outside the auction, and at whose cost (§2, §3)LIKELY
Sep 15–16, 2026NERC Data Center Load Modeling WorkshopSets the modeling conventions the year-end standard will codify (§4, T.4)SETTLED
Sep 16, 2026Stakeholder comments on RTO show-cause filings dueLast broad intervention window before FERC acts (§7)SETTLED
Oct 20 / 28, 2026CAISO WEM Governing Body and Board of Governors votes on the large-load packageWhether the abeyance route produces a §205 proposal rather than a defence of the tariff (§7)LIKELY

Table W1 — The next ninety days. Dates already fixed by an order, a rule, or a filing deadline. Confidence tags refer to the outcome, not the date: the calendar is settled even where what it produces is not.

Sources: FERC; NERC; ERCOT; PUCT; PJM; MISO; SPP; DOE, from the filings and dockets listed in the Catalog of Orders, Rules, and Directives Cited.

Q4 2026 through Q1 2027 — obligations begin to bind#

Here voluntary guidance becomes enforceable. The December 31 date may prove the most consequential entry on the list, because reliability obligations then attach to the load itself rather than to the utilities around it.

DateEventWhat it decidesTag
Mid-Nov 2026CAISO filing on the show-cause order; §205 filings from any other region granted an abeyanceWhether the regions that take the pause file tariff proposals rather than defend the existing tariff (§7)EMERGING
Q4 2026First NERC large-load Reliability Standard (Project 2026-02 “bridge” standard)Converts voluntary guidance into enforceable obligation (§4)LIKELY
Dec 2026PUCT duplicate-request disclosure rule final (16 TAC §25.194)Determines the honest size of the ERCOT queue (§1)LIKELY
**Dec 31, 2026****RD26-7-000 compliance:** NERC files Reliability Standards **and** Rules-of-Procedure registration criteria for computational loadsA central reliability reform lands on a date certain; the registry threshold remains the open question (§4, §8)SETTLED
Dec 2026 – Jan 2027NERC Long-Term Reliability Assessment (annual)Whether the ten-year peak forecast is revised upward again (§1, §9)LIKELY
**Mar 1, 2027****RD26-7-000:** NERC Phase II work plan for additional standards dueSets the trajectory for standards beyond the bridge rule (§4)SETTLED
Mar 2027PJM reliability backstop — central pay-as-bid procurementPrice and cost allocation of backstop capacity billed to large loads (§2, §3)LIKELY

Table W2 — Late 2026 into 2027, where guidance becomes obligation. These are the dates at which the reforms described throughout the report stop being proposals and start carrying compliance consequences.

Sources: FERC; NERC; ERCOT; PUCT; PJM; MISO; SPP; NYISO; state commissions.

Through 2027 and into 2028 — the rules mature, the risk window opens#

The later entries grow increasingly uncertain because they depend on future rulemakings, and they also make the report's central timing inversion visible: the reliability-risk windows open in 2028 while the remedial standards are still being drafted and the major transmission is still years from energization.

DateEventWhat it decidesTag
Across 2027FERC RM26-4 matures from ANOPR to NOPR and then final ruleWhether a pro forma national large-load interconnection procedure exists at all (§1, §7)SPECULATIVE
2027NERC Phase II computational-load standards drafted; registry populatedScope thresholds decide which facilities are actually bound (§4, §8)SPECULATIVE
2027Co-location and flexible-load service terms take effect after the rulemakingWhether non-firm service is priced attractively enough to be chosen (§5, §6)SPECULATIVE
Mid-2027PJM Base Residual Auction for the 2029/30 delivery yearA third consecutive shortfall would confirm scarcity is structural, not cyclical (§2, §3)LIKELY
Jul 2027New York moratorium lapses; GEIS and Energize NY framework dueA framework other states may adopt, modify, or decline (§7)LIKELY
2027–2028ERCOT 765 kV backbone and Permian Basin plan construction milestonesThe long-lead wires that do not actually arrive until the 2030s (§9)SPECULATIVE
2028MISO enters the NERC elevated/high reliability-risk windowOpening of the gap where risk bites before the fixes are enforceable (§9)SPECULATIVE
Jun 1, 2028PJM 2028/29 delivery year begins — the year procured ~6.8 GW shortFirst delivery year in PJM history to start below the reliability requirement (§2)SETTLED

Table W3 — 2027 and beyond. Tagged Speculative where the entry depends on a rulemaking that has not yet been proposed, or on a market outcome three years out. The dates are indicative; the direction is not.

Sources: NERC Long-Term Reliability Assessment; ERCOT; PJM; MISO; FERC.

The near-term entries in this table are the operational watch list; Section 9 carries the full 2018–2035 view, including the long-lead physical builds beyond this horizon.

Cite as: Zavadsky, V. (2026). Large-Load Grid Integration: A Primer: The Eight Problems — and the Decade That Frames Them (v1.31). Zenodo. 10.5281/zenodo.21464969
Data current through July 21, 2026. Generated from the same source as the PDF edition.